The largest expansion of the parking area with a capacity for 70 large aircraft begins at Teruel Airport-Noticias
Por plata en Viernes, 11 Octubre 2024
Categoría: news

The largest expansion of the parking area with a capacity for 70 large aircraft begins at Teruel Airport

The Teruel Airport Consortium continues to take firm steps in its Strategic Plan 2024-27, and that is why work has begun on the phase V parking lot at its facilities. This is the largest extension of the parking lot, located in the PIGA area, and will allow 70 large aircraft to be parked in the new area.

The work began at the end of September 2024, and was awarded to the UTE EXCAVACIONES HNOS. DE PABLO S.L - VIALEX CONSTRUCTORA ARAGONESA S.L. - EMIPESA S.A. with a term of execution of 15 months, with its completion scheduled for the end of December 2025. The award amount is 12,080,179.87 euros (VAT excluded). The start-up deed was signed on September 23, 2024.

The Health and Safety Plan, the Operational Safety Surveillance Plan, the Waste Management Plan, the Quality Plan and the updated construction plan have already been drawn up, in addition to the opening of the work centre and the enabling of the subcontracting book. Within the administrative process, the start of the work has been communicated to the CHJ and Highways of the Government of Aragon.

Since the start of the work 2 weeks ago, the 10 workers currently present have carried out the compaction of the storage area, as well as the installation of the construction sheds. The first months of the work will consist mainly of clearing the land and moving earth, planned until March 2025. Once this process is finished, an increase in activity and the number of workers is expected, with an average of 50 workers per day expected to be reached.

Regarding the more specific characteristics of the work, the same structure will be followed as in the previous 4 phases of the parking lot:

PIGA zone

Machinery for clearing

Actual aircraft storage